1 (a)
What is outsourcing? What are its advantages and disadvantages?
5 M
1 (b)
What is project management? Why is it needed?
5 M
1 (c)
Define project. What are the attributes of project?
5 M
1 (d)
What is project integration management?
5 M
1 (e)
What is relation between MOV, scope and WBS
5 M
2 (a)
Explain project procurement management.
10 M
2 (b)
What are the methods of budgeting for a project?
10 M
3 (a)
Explain the project Scheduling techniques.
10 M
3 (b)
Explain IT project risk identification framework.
10 M
4 (a)
Explain the various leadership styles.
10 M
4 (b)
Explain the project change management plan.
10 M
5 (a)
Explain scope management plan.
10 M
5 (b)
Explain the project implementation approaches.
10 M
6 (a)
Explain project planning framework.
10 M
6 (b)
Define critical path. Draw AON diagram and find critical path for
Activity | Predecessor | Duration in days |
A | - | 2 |
B | A | 5 |
C | A | 2 |
D | B | 5 |
E | B | 5 |
F | C | 5 |
G | D | 1 |
H | D | 1 |
I | G | 2 |
J | E, F, H, I | 1 |
10 M
Write short note on any two:
7 (a)
Resource loading and resource levelling.
10 M
7 (b)
Dealing with resistance and conflicts in project.
10 M
7 (c)
Project communication plan
10 M