MU Information Technology (Semester 7)
Software Project Management
May 2014
Total marks: --
Total time: --
INSTRUCTIONS
(1) Assume appropriate data and state your reasons
(2) Marks are given to the right of every question
(3) Draw neat diagrams wherever necessary


1(A) Solve are PMBOK knowledge areas?
5 M
1(B) Compare various project implementation approaches.
5 M
1(C) What is the need of IT project management?
5 M
1(D) Compare various formal organizational structure.
5 M
1(E) Define:
Scope grope,
Scope creep
Scope leap
Projectities
Earned values.
5 M

2(A) Define project.Explain the attributes of project.
10 M
2(B) Explain project estimation techniques.
10 M

3(A) Explain the phases of project life cycle.Compare it with SDLC.
10 M
3(B) What is outsourcing?Explain project procurement management.
10 M

4(A) Explain IT project risk identification framework.
10 M
4(B) Explain the change management plan.
10 M

5(A) Explain the practices of exemplary leadership.What are the leadership styles?
10 M
5(B) Explain scope management processes.
10 M

6(A) Explain project planning framework
10 M
6(B)

Define critical path.Draw AON diagram, find critical path and float non critical path for following:

Activity Predecessor Duration in days
A --------- 6
B A 5
C A 8
D B,C 4
E C 3
F D 2
G D 4
H E,F,G 7
10 M

Any Two
7(A) Write short on any
Ethical leadership and ethical dilemmas
10 M
7(B) Resource loading
10 M
7(C) Project communication management
10 M
7(D) Work break down structure
10 M