Write short note on any four Q1 (a,b,c,d,e)
1(a)
Administrative approval
5 M
1(b)
CBRI equation
5 M
1(c)
Mass Haul Diagram and its improtance
5 M
1(d)
Freehold and Lease hold property
5 M
1(e)
Cross drainge works
5 M
2(i)
Determine an Detailed estimate of a residential building ( R.C.C. framed structure) located in Vashi, Navi Mumbai.
i) Earthwork excavation in foundation
i) Earthwork excavation in foundation
4 M
2(ii)
Plain cement concrete (1:4:8) in foundation
4 M
2(iii)
Brick masonry in C.M. 1:6 for sub-structure.
4 M
2(iv)
R.C.C work in footings,
columns,
plinth beam,
chajjas,
roof beams and roof slab
columns,
plinth beam,
chajjas,
roof beams and roof slab
8 M
3(a)
Carry out the rate analysis for
i) M 20 grade R.C.C concrete wit 2% steel including fromwork and reinforcement.
ii) Internal plastering in C.M. 1:5.
i) M 20 grade R.C.C concrete wit 2% steel including fromwork and reinforcement.
ii) Internal plastering in C.M. 1:5.
10 M
3(b)
Draft a tender call notice for the construction of a Water treatment plant in Mumbai. It is estimated to cost 30 crores and is to be completed in 20 calender months.
10 M
4(a)
Prepare an estimate for residential building in the western suburbs of Mumbai (R.C.C. framed structure)
i) plat area -80m×50m
ii) FSI - 1.5
iii) Building is G+6
iv) Consider the foundation cost as 18% of super structure cost
v) Allow 22% of building cost of all services
vi) Allow 2.5% of overall cost for consultant fees
vii) Consider 5.0% provision for contingencies
i) plat area -80m×50m
ii) FSI - 1.5
iii) Building is G+6
iv) Consider the foundation cost as 18% of super structure cost
v) Allow 22% of building cost of all services
vi) Allow 2.5% of overall cost for consultant fees
vii) Consider 5.0% provision for contingencies
7 M
4(b)
Differentiate between:
i) Security Deposit and Earnest Money Deposit
ii) Day's work and Piece work
i) Security Deposit and Earnest Money Deposit
ii) Day's work and Piece work
5 M
4(c)
Work out the earthwork quantities in embankment and cutting for a length of 600 m. The particulars are:
i) Formation width =20m
ii) Side slopes in embankment =2:1(H.V) in cutting =1.5:1 (H.V.)
iii) There is no transverse slope
iv) Rising gradient of 1:250 upto 250 m chain age
v) Rising gradient of 1:100 upto 600 m chain age
i) Formation width =20m
ii) Side slopes in embankment =2:1(H.V) in cutting =1.5:1 (H.V.)
iii) There is no transverse slope
iv) Rising gradient of 1:250 upto 250 m chain age
v) Rising gradient of 1:100 upto 600 m chain age
Chainage | 0 | 50 | 100 | 150 | 200 | 250 | 300 | 400 | 450 | 500 | 550 | 600 |
R.L.of Ground | 172.0 | 172.35 | 172.60 | 173.80 | 173.0 | 172.65 | 172.20 | 171.20 | 170.65 | 170.35 | 170.60 | 170.75 |
R.L.of Formation | - | 171.60 | - | - | - | 172.40 | - | - | - | - | 175.40 | - |
8 M
5(a)
What is bar bending schedule? What is its importance? Prepare a bar bending schedule of the figure shown in Fig.in.2. The Roof Slab is 3 metres clear span and 6 metres long. (In plan, top and bent up bars are shown in dotted lines).
10 M
5(b)
What is pre-bid conference? Explain pre-qualification of contractor and why is it required.
5 M
5(c)
Work out the quantities of material required for M25 grade concrete in slabs and beams, 200 cu.mt. In quantity with 1.75% steel and 0.45 water to cement ration (by weight). Also give the unit rates Also give the unit rates of the materials.
5 M
6(a)
Explain Belting Method of valuation of property with an example.
5 M
6(b)
A newly constructed building costs Rs. 68 lakhs on a polt of valuation of Rs.85 lakhs. In this plot, flats of 120m2 each are constructed. Fix the monthly rent per flat from the following data:
i) Net return on land and building = 7.5%
ii) Life of building = 60 years
iii) Interest rate on Sinking Fund = 6%
iv) Salvage Value = 10% of the cost of the building
v) Repairs and Maintenance = 2.5% of the building cost
vi) Taxes and Other Expenses = 20% of the gross rent
No of flats = 10
i) Net return on land and building = 7.5%
ii) Life of building = 60 years
iii) Interest rate on Sinking Fund = 6%
iv) Salvage Value = 10% of the cost of the building
v) Repairs and Maintenance = 2.5% of the building cost
vi) Taxes and Other Expenses = 20% of the gross rent
No of flats = 10
10 M
6(c)
What is meant by depreciation? Explain Sinking Fund Method of Depreciation. !mage
5 M
More question papers from Quantity Survey, Estimation and Valuation