1
Work out the quantities of the following items of work by referring plan & section shown in Fig.1
a) P.C.C(1:2:4) in foundation.
b) 1 st Class brickwork in foundation in C.M(1:4)
c) 2.5 cm thick D.P.C(1:3:6)
d) 12 mm thick internal plaster in C.M(1:5) Schedule of openings :-
a) P.C.C(1:2:4) in foundation.
b) 1 st Class brickwork in foundation in C.M(1:4)
c) 2.5 cm thick D.P.C(1:3:6)
d) 12 mm thick internal plaster in C.M(1:5) Schedule of openings :-
Doors | Windows |
D1 = 1.1 m × 2.1 m | W1 = 2.0 m × 1.3 m |
D2 = 1.0 m × 2.1 m | W2 = 1.8 m × 1.3 m |
D3 =0.9 m × 2.1 m | W3 = 1.5 m × 0.8 m |
O = 1.2 m × 2.1 m | V = 0.6 m × 0.4 m |
Wall Thickness = 300 mm
Plinth level = 600 mm
Floor to floor height = 3000 mm
Slab thickness = 120 mm
20 M
2 (a)
Prepare an approximate estimate for (G+4) R.C.C building. Bldg consist of six flats on each floor & each flat has carpet area of 110m2. Assume area occupied by walls & columns etc. As 10% of built up area of circulation as 20% of built up area. Assume cost of construction as Rs 10000/m2.
10 M
2 (b)
Prepare abstract of cost for the items in Q no 1.
6 M
2 (c)
What is Tender Notice? Mention main inclusions of it.
4 M
3 (a)
What is contract? Explain the types of contract with their suitability.
12 M
3 (b)
Prepare rate analysis for 1 st class brickwork in super structure in C.M(1:4)
8 M
4 (a)
Work out the quantity of earthwork for a portion of a road
1) Top width of formation=12m
2) RL of formation at zero chainage=51.4m
3) Falling Gradient=1 in 200
4) Side slope-1V:2H(Banking )1V:1.5H(Cutting)
1) Top width of formation=12m
2) RL of formation at zero chainage=51.4m
3) Falling Gradient=1 in 200
4) Side slope-1V:2H(Banking )1V:1.5H(Cutting)
Chainage | 0 | 30 | 60 | 90 | 120 | 150 | 180 |
R.L of Gr.(m) | 50.8 | 80.6 | 50.7 | 51.2 | 51.4 | 51.3 | 51 |
12 M
Explain
4 (b) (i)
Mass Haul Diagram.
4 M
4 (b) (ii)
Prismoidal formula & Trapezodial formula.
4 M
Explain
5 (a) (1)
Eamest money deposit & Security Deposit.
4 M
5 (a) (2)
Liquidated Damages and unliquidated damages.
4 M
5 (a) (3)
Freehold properties & Leasehold properties.
4 M
5 (b)
Explain Belting Method of Valuation in detail.
8 M
6 (a)
A building is newly constructed with cost of Rs.1 Crore over a plot of land costing Rs.70 lacs Building Consists of 20 flats of area 120M2 each work out monthly standard rent/ flat from the following data :
1) Expected net return from land & building=7%
2) Rate of interest on sinking fund=9%
3) Life of building=60 years.
4) Salvage value=10% of cost of building cost.
5) Repairs & maintenance cost=7% of building cost.
6) Taxes & other outgoings=25% of gross rent.
1) Expected net return from land & building=7%
2) Rate of interest on sinking fund=9%
3) Life of building=60 years.
4) Salvage value=10% of cost of building cost.
5) Repairs & maintenance cost=7% of building cost.
6) Taxes & other outgoings=25% of gross rent.
10 M
6 (b)
What is bar bending schedule? Why it is prepared? Explain clearly along with its proforma.
6 M
Explain
6 (c) (i)
Pre-bid conference.
2 M
6 (c) (ii)
Debitable agency.
2 M
Write short note on (any four)
7 (a)
Escalation clause.
5 M
7 (b)
C.B.R.I method.
5 M
7 (c)
I.S. 1200
5 M
7 (d)
Freehold properties & Leasehold properties.
5 M
7 (e)
Use of computers in Estimation process.
5 M
More question papers from Quantity Survey, Estimation and Valuation