Work out the qualities from given plan & section:-
1 (a)
Excavation in ordinary soil.
5 M
1 (b)
UCR masonry in foundation in C.M(1.4).
5 M
1 (c)
RCC quantities for slab, band lintel (150mm thick) and chajja in M25 grade of concrete.
5 M
1 (d)
External plastering in C:M1:3, 15 mm thick.
5 M
2 (a)
Prepare an abstract for the cost of the items of work in Question 1.
8 M
2 (b)
Draft detailed specifications for
i) RCC (1.1, 5:3) in slabs, beams, lintels and staircase.
ii) 20 mm thick external plaster in C.M(1:4)
i) RCC (1.1, 5:3) in slabs, beams, lintels and staircase.
ii) 20 mm thick external plaster in C.M(1:4)
12 M
3 (a)
Prepare an approximate estimate for the construction of (G+10) storeyed residential building to be constructed in newly developing suburbs of Mumbai. The building comprises of five flats per floor, each that admeasuring 140 square metres. Assume suitable cost of construction.
10 M
3 (b)
Draft a tender notice for the construction of a water treatment plant of an estimated cost 10 crores. The duration of project is 18 months.
10 M
Prepare rate analysis for
4 (a) (i)
P.C.C (1-5:10)in foundation bed.
5 M
4 (a) (ii)
1st class Burnt Brick Masonry in super structure in C.M 1:4
5 M
Differentiate between
4 (b) (i)
Revised Estimate and Supplementary Estimate.
3 M
4 (b) (ii)
Depreciation and Obsolescence.
3 M
4 (b) (iii)
Liquidated Damages and non liquidated damages.
4 M
5 (a)
Calculate the quantity of reinforcement by preparing bar bending schedule for fig given below.
10 M
5 (b)
A person has purchased a plot of land costing Rs 7,00,000/ and has constructed a building there on at a cost of Rs. 20,00,000/ including W/S sanitary electrical installations. Allowing a net return @ 8.5% on cost of construction and @ 5% net return on the cost of land work out standard rent of the property with the following data :-
i) Sinking found on 4% basis for the future life of 80years=0.0022
ii) Annual maintenance -1/2 % of cost of construction.
iii) Municipal taxes and other outgoings- 28.5% of gross rent.
i) Sinking found on 4% basis for the future life of 80years=0.0022
ii) Annual maintenance -1/2 % of cost of construction.
iii) Municipal taxes and other outgoings- 28.5% of gross rent.
10 M
6 (a)
Explain different types of Acts pertaining to the construction industry.
10 M
6 (b)
Find the quantity and cost of material's for the following works.
i) 275 sqm. Internal plaster 12mm thick in C.M(1:4)
ii) 120 cm RCC (1:1.5:3) with 2% steel.
iii) 400m2 flooring with vitrified tiles
i) 275 sqm. Internal plaster 12mm thick in C.M(1:4)
ii) 120 cm RCC (1:1.5:3) with 2% steel.
iii) 400m2 flooring with vitrified tiles
10 M
Write short note on (any four)
7 (a)
Eamest money Deposit.
5 M
7 (b)
Arbitrary Tribunal
5 M
7 (c)
CBRI method of approximate estimate.
5 M
7 (d)
IS-1200
5 M
7 (e)
Belting Method Of Valuation
5 M
More question papers from Quantity Survey, Estimation and Valuation