MU Instrumentation Engineering (Semester 8)
Instrumentation Project Documentation and Execution
May 2015
Instrumentation Project Documentation and Execution
May 2015
Answer the following (Any Four):
1 (a)
Define project and explain term predictability related to project.
5 M
1 (b)
Explain conduit and tray schedule.
5 M
1 (c)
Explain Sequential Function Chart (SFC) with example.
5 M
1 (d)
Explain the role of designer.
5 M
1 (e)
Explain ISA tagging process to indicate the instrument and its function.
5 M
2 (a)
Explain Project planning in details.
10 M
2 (b)
Draw and explain electronic and pneumatic loop writing diagram for level control loop.
10 M
Explain the following:
3 (a) (i)
Junction box schedule
5 M
3 (a) (ii)
Air header schedule.
5 M
3 (b)
Explain Factory Acceptance Test and Site Acceptance test.
5 M
4 (a)
Draw and explain hook up diagram for flow and temperature measurement.
10 M
4 (b)
Explain in short HMI specification
10 M
5 (a)
Explain the specification sheet for DP transmitter and control valve.
10 M
5 (b)
Describe the different Standards used for instrumentation project.
10 M
6 (a)
Draw and explain the Instrument location plans with example.
10 M
Explain the following project activity:
6 (b) (i)
O & M manual
5 M
6 (b) (ii)
Commissioning
5 M
Write a short note on any two:
7 (a)
Project Deliverables
10 M
7 (b)
Checkout procedure for Temperature transmitter and control valve.
10 M
7 (c)
Software packages for Documentation.
10 M
More question papers from Instrumentation Project Documentation and Execution