SPPU Information Technology (Semester 6)
Information Tech Project Management
December 2015
Total marks: --
Total time: --
INSTRUCTIONS
(1) Assume appropriate data and state your reasons
(2) Marks are given to the right of every question
(3) Draw neat diagrams wherever necessary


Solve any one question from Q1 and Q2
1 (a) State the difference between:
i) High level design and detailed design.
ii) Unit testing and system testing.
4 M
1 (b) Explain process used for decision making.
3 M
1 (c) Explain bottom up approach in effort estimation during project Planning.
3 M

2 (a) Explain the concept of SWOT analysis.
4 M
2 (b) Why all engineers need leadership skills?
3 M
2 (c) Write short note on Six sigma Process.
3 M

Solve any one question from Q3 and Q4
3 (a) Explain 4 Ms in resources for project.
4 M
3 (b) What are essential qualities a person should have to lead technical people?
6 M

4 (a) What is process capability baseline? Explain outcomes of it.
4 M
4 (b) Enlist any 6 essential contents of proposal in Project initiation.
6 M

Solve any one question from Q5 and Q6
5 (a) What are steps in Project monitoring and control?
8 M
5 (b) Explain in short importance of HR management and communication management in Project execution.
8 M

6 (a) What are essential contents of any Project management plan?
8 M
6 (b) Order following 6 processes of Time Management in proper sequence and explain each of them.

Schedule control
Activity Duration estimation
Schedule Development
Activity Sequencing
Activity Definition
Activity Resource estimating
8 M

Solve any one question from Q7 and Q8
7 (a) What are the risks and benefits of ERP?
8 M
7 (b) Explain any 8 success factors for ERP implementation.
8 M

8 (a) What is ERP? Why it is important to a company?
8 M
8 (b) Explain ERP implementation Life cycle.
8 M

Solve any one question from Q9 and Q10
9 (a) Explain concept of Supply chain management with suitable example.
8 M
Write short note on:
9 (b) (i) Software configuration management.
5 M
9 (b) (ii) Reverse Engineering.
5 M

10 (a) What are essential features of any IT Project management tool?
8 M
Write short note on:
10 (b) (i) Reengineering.
5 M
10 (b) (ii) Software maintenance.
5 M



More question papers from Information Tech Project Management
SPONSORED ADVERTISEMENTS