MU Civil Engineering (Semester 3)
Surveying - 1
December 2014
Total marks: --
Total time: --
INSTRUCTIONS
(1) Assume appropriate data and state your reasons
(2) Marks are given to the right of every question
(3) Draw neat diagrams wherever necessary


1 (a) Explain cumulative and compensating errors in chaining.
4 M
1 (b) Describe temporary adjustment of prismatic compass.
4 M
1 (c) Explain the reciprocal levelling and state its advantages.
4 M
1 (d) Differentiate between consecutive co-ordinate and independent coordinate.
4 M
1 (e) Explain the characteristics of contour lines.
4 M
1 (f) Explain geodetic surveying.
4 M

2 (a) Write short notes on compound levelling and profile levelling.
5 M
2 (b) A chaining pass a porid,stations P and Q were selected on opposite side of the pond. A line PA,200 m long, was set out of the left of PQ ,and a line PB was set out on the right such that A,Q and B are collinear. The length of PB was 250m. The length of AQ and QB were meassured to be 125m and 150m respectively. The chainage at P is 1020.55m. Calculate the chainage of Q.
5 M
2 (c) The following bearings were observed while traversing with compass. Find which stations are affected by local attractions and work out corrected bearing of the lines of closed traverse.
Line F.B. B.B.
AB 191° 30' 13° 0'
BC 69° 30' 246°30'
CD 32° 15' 210° 30'
DE 262° 45' 80° 45'
EA 230° 15' 53° 00'
10 M

3 (a) Write exhaustive note on 'obstacles in chaining'.
5 M
3 (b) Explain the various type of bench marks used in levelling.
5 M
3 (c) The following staff reading were observed with a level & a 4 m staff on a continuously sloping ground at a common nterval of 15m. The reading are 0.880,1.632,2.530,3.085,3.580,1.255,2.060,2.465,3.740,1.035,1.145,1.1730 and 2.645. The reduced level of the first point was 780.150. Rule out a page of level-book and enter the above reading. Calculate the reduced levels and the gradient of the line joining the first & last points.
10 M

4 (a) Define two point problem & explain how it can be solved on field.
8 M
4 (b) Balance the following closed traverse by transit rule and also compute the closing error?
Line Lat (m) Dep (m)
AB -173.20 100.00
BC -314.50 128.40
CD 86.60 50.00
DE 250.00 0.00
EA 154.90 -280.00
12 M

5 (a) Explain the method of measuring and recording horizontal angle by repetition method using transit?
10 M
5 (b) The following offsets were taken from a chain line to a hedge
Distance (m) 0 5 12 18 24 36 48 60 72 81 90
Offset (m) 3.8 3.3 2.4 1.8 0.9 1.5 1.8 2.2 3 3.3 3.6

Calculate the area enclosed between the chan-line, the hedge and the end-offsets by simpson's rule & trapezoidal rule.
10 M

Write short note on any four.
6 (a) Hypotenusal allowance.
5 M
6 (b) Types of variations.
5 M
6 (c) Sources of error in levelling.
5 M
6 (d) Spire test.
5 M
6 (e) Orientation in plane table surveying.
5 M



More question papers from Surveying - 1