JOBS | ||||
MACHINES
Soaking |
1 6 4 1 2 8 |
2 5 5 3 4 9 |
3 4 3 4 5 7 |
4 7 2 2 1 5 |
Determine the total elapsed time and also find the idle time of each machine.
Worker | JOBS | |||||
P | Q | R | S | T | U | |
1 2 3 4 5 |
20 15 11 8 12 |
15 32 15 24 20 |
26 46 2 12 18 |
40 26 12 22 10 |
32 28 6 22 22 |
12 20 14 20 15 |
Only one job can be assigned to one worker. Determine how the jobs should be allocated so as to minimize the total work houRs. Also find total work houRs.
Month |
Demand (in units of product) |
Jan Feb Mar Apr May Jun |
40 70 60 120 100 90 |
i) What would the forecast be for all the months, if exponential smoothing method is used, with a=0.2 and forecast for January of 30 units.
ii) What would the forecast for May have been, if made at the end of April, using a four month moving average.
iii) What would be the mean absolute deviation (MAD) for all the six months using the forecasts obtained by the exponential smoothing method as used above.
Maximum | Z=4x1+5x2-3x3 |
Subject to: | x1+x2+x3=10 |
x1-x2 ?1 | |
2x1+3x2+x3 ? 40 | |
x1, x2, x3 ? 0 |
Month | Jul | Aug | Sep | Oct | Nov | Dec |
Demand | 3500 | 3700 | 3900 | 4000 | 3400 | 3600 |
Working day | 25 | 23 | 21 | 24 | 23 | 22 |
production Details: Safely Stock of 200 units per month, Beginning inventory of 500 units, No. of workers is 20 labour hours required is 10 hr/unit, Materials cost is Rs. 100/unit, Inventory carrying cost is Rs. 100/unit/month, Cost of shortage is Rs. 200/unit/month, Cost of subcontracting is Rs. 500/unit, Hiring and training costs is Rs. 250/worker, Layoff cost is Rs. 400/worker, regular production time labour cost (first 8 hours)=Rs. 20/hour. Overtime cost is Rs. 30/hour.
Determine the total production cost of using constant workforce and using subcontracting only and not carrying forward any excess inventory (include material production costs also).
Let size=200 units and lead time of 1 week and safely stock=zero units.
weekly requirements: week 1=50 units, week 2=150 units, week 3=180 units, week 4=80 units, week 5=12.0 units, week 6=220 units and week =150 units.
Inventory on hand = 210 units
If the inventory on hand changes to 60 units and a scheduled receipt of 100 units is expected to arrive in week 2, redraw the MRP plan and recalculate the table.
Delhi | Mumbai | Kolkata | Nagpur | Bangalore | |
Chennai Noida Hyderabad |
8 4 8 |
8 7 4 |
6 7 6 |
6 6 6 |
3 5 4 |
Determine an optimum distribution for the company in order to minimize the total transportation costs.
Activity | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
Preceding Activity |
- | - | - | A | A |
B, D |
C | A | C | C |
E, F, G |
H, I |
L |
J, K |
Activity Duration |
3 | 5 | 6 | 7 | 4 | 2 | 4 | 6 | 5 | 7 | 4 | 6 | 3 | 3 |