| JOBS | ||||
|
MACHINES
Soaking |
1 6 4 1 2 8 |
2 5 5 3 4 9 |
3 4 3 4 5 7 |
4 7 2 2 1 5 |
Determine the total elapsed time and also find the idle time of each machine.
| Worker | JOBS | |||||
| P | Q | R | S | T | U | |
|
1 2 3 4 5 |
20 15 11 8 12 |
15 32 15 24 20 |
26 46 2 12 18 |
40 26 12 22 10 |
32 28 6 22 22 |
12 20 14 20 15 |
Only one job can be assigned to one worker. Determine how the jobs should be allocated so as to minimize the total work houRs. Also find total work houRs.
| Month |
Demand (in units of product) |
|
Jan Feb Mar Apr May Jun |
40 70 60 120 100 90 |
i) What would the forecast be for all the months, if exponential smoothing method is used, with a=0.2 and forecast for January of 30 units.
ii) What would the forecast for May have been, if made at the end of April, using a four month moving average.
iii) What would be the mean absolute deviation (MAD) for all the six months using the forecasts obtained by the exponential smoothing method as used above.
| Maximum | Z=4x1+5x2-3x3 |
| Subject to: | x1+x2+x3=10 |
| x1-x2 ?1 | |
| 2x1+3x2+x3 ? 40 | |
| x1, x2, x3 ? 0 |
| Month | Jul | Aug | Sep | Oct | Nov | Dec |
| Demand | 3500 | 3700 | 3900 | 4000 | 3400 | 3600 |
| Working day | 25 | 23 | 21 | 24 | 23 | 22 |
production Details: Safely Stock of 200 units per month, Beginning inventory of 500 units, No. of workers is 20 labour hours required is 10 hr/unit, Materials cost is Rs. 100/unit, Inventory carrying cost is Rs. 100/unit/month, Cost of shortage is Rs. 200/unit/month, Cost of subcontracting is Rs. 500/unit, Hiring and training costs is Rs. 250/worker, Layoff cost is Rs. 400/worker, regular production time labour cost (first 8 hours)=Rs. 20/hour. Overtime cost is Rs. 30/hour.
Determine the total production cost of using constant workforce and using subcontracting only and not carrying forward any excess inventory (include material production costs also).
Let size=200 units and lead time of 1 week and safely stock=zero units.
weekly requirements: week 1=50 units, week 2=150 units, week 3=180 units, week 4=80 units, week 5=12.0 units, week 6=220 units and week =150 units.
Inventory on hand = 210 units
If the inventory on hand changes to 60 units and a scheduled receipt of 100 units is expected to arrive in week 2, redraw the MRP plan and recalculate the table.
| Delhi | Mumbai | Kolkata | Nagpur | Bangalore | |
|
Chennai Noida Hyderabad |
8 4 8 |
8 7 4 |
6 7 6 |
6 6 6 |
3 5 4 |
Determine an optimum distribution for the company in order to minimize the total transportation costs.
| Activity | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
|
Preceding Activity |
- | - | - | A | A |
B, D |
C | A | C | C |
E, F, G |
H, I |
L |
J, K |
|
Activity Duration |
3 | 5 | 6 | 7 | 4 | 2 | 4 | 6 | 5 | 7 | 4 | 6 | 3 | 3 |
STUPIDSID