VTU Mechanical Engineering (Semester 7)
Operations Research
June 2014
Total marks: --
Total time: --
INSTRUCTIONS
(1) Assume appropriate data and state your reasons
(2) Marks are given to the right of every question
(3) Draw neat diagrams wherever necessary


1 (a) List and explain the various phases of OR problems
6 M
1 (b) What are the limitations of OR?
4 M
1 (c) A manufacturer of a line of patent medicines is preparing a production plan on medicines A and B. There are sufficient ingredients available to make 20,000 bottles of A' and 40,000 bottles of B'. But three are only 45,000 bottles into which either of the medicines can be put. Further more. it takes 3 hours to prepare enough material to till 1.000 bottles of A. it takes 1 hour to prepare enough material to fill 1,000 bottles of 'B' and there are 66 hours available for this operation. The profit is Rs 8 per bottle for 'A' and Rs 7 per bottle for 'B'. formulate the problem as a LPP and solve by graphical method
10 M

2 (a) Define slack, surplus, and artificial variables,
6 M
2 (b) Obtain the dual of the following primal LP problem:
Minimize Z- x1+x2+x3
Subject to x1-3x2+4x3-5 ; 2x1-2x2\le3
x1 +2x3\ge30 ; x1, x2\ge0
10 M

3 (a) A company has plants A, B and C which have capacity to produce 300, 200 and 500 kg respectively of a particular chemical/day. The production cost per kg in these plants are Rs0.70, Rs0.60 and Rs 0.66 respectively. Four bulk consumers have. placed orders for the products on the following books
Consumer Kg required / day Price offered Rs/kg
I 400 1.00
II 250 1.00
III 350 1.02
IV 150 1.03

Shipping costs in paise/kg from plants to consumer are given below
  I II III IV
A 3 5 4 6
B 8 11 9 12
C 4 6 2 8

Workout the optimum schedule for the above situation considering all the data given
12 M
3 (b) company has a team of four salesman and there are four districts where the company wants to start its business. The company estimates that the profit/day is given below. Find the assignment of salesman to districts which gives maximum profit.
  I II III IV
A 16 10 14 11
B 14 11 15 15
C 15 15 13 12
D 13 12 14 15
8 M

4 (a) Explain the branch and bound method in integer programming
6 M
4 (b) Use Gomary's' fractional cutting plane method to solve the following IPP
Minimize Z=x1+4x2
5x1-4x2\le15
x1,x2\ge 0 and are integers
14 M

5 (a) List the differences between PERT and CPM
5 M
5 (b) A small project consists of EIGHT activities has the following characteristics.
Activity Preceding activity Times estimate (weeks)
tu tm tp
A - 2 4 12
B - 10 12 26
C A 8 9 10
D A 10 15 20
E A 7

7.5

11
F B,C 9 9 9
G D 3 3.5 7
H E,F,G 5 5 5

(i) Draw the PERT network for the project.
(ii) Determine the critical path and prepare the activity schedule for the project.
(iii) If a 30 week deadline is imposed. what is the probability that the project will be completed within the time limit?
15 M

6 (a) Briefly explain the queuing system and their characteristics
6 M
6 (b) A postal clerk can service a customer in 3 minutes. The service time is being exponentially distributed. The inter arrival time of customers is also experimentally distributed with an average of 12 minutes during early morning slack period and an average of 5 minutes during the afternoon peak period. Assess the average queue length and the expected waiting time in the queue during the two periods
14 M

7 (a) Explain the following
i) Pay off matrix ii) Saddle point iii) Fair game
5 M
7 (b) Explain the rule of dominance
3 M
7 (c) Use of property of dominance to solve the following game
  I II III IV V VI
I 0 0 0 0 0 0
II 4 2 0 2 1 1
III 4 3 1 3 2 2
IV 4 3 7 -5 1 2
V 4 3 4 -1 2 2
VI 4 3 3 -2 2 2
12 M

8 (a) State the assumptions made while dealing with sequencing problems
4 M
8 (b) Find the sequence for the following six jobs that will minimize the total elapsed time for the three operations
Job 1 2 3 4 5 6
Turning (A) 3 12 5 2 9 11
Threading (B) 8 6 4 6 3 1
Knurling (c) (Time in minute) 13 14 9 12 8 13
6 M
8 (c) Use graphical method m minimi7c the time required to process the following jobs on the machines. Calculate the total elapsed time to complete the jobs. For each machine specify the job that should be done first
  Machine
Job 1 Sequence: A B C D E
Time (hr) : 6 8 4 12 4
Job 2 Sequence : B C A D E
Time (hr) : 10 8 6 4 12
10 M



More question papers from Operations Research
SPONSORED ADVERTISEMENTS