1 (a) Explain the various methods of determining average rainfall over a catchment due to storm. Discuss relative merits and demerits of each.
7 M
1 (b) Define unit hydrograph. Describe the procedure of deriving a unit hydrograph from a given flood hydrograph.
7 M

2 (a) 1 Explain the following terms:
1. Precipitation.
2.Infiltration capacity.
3.Evapo-transpiration.
4.Infiltration Rate.
5.Hydrograph.
6.Floods
7.Drought.
7 M
2 (b) Describe in detail the factors affecting infiltration.
7 M
2 (c) A storm with 11cm precipitation produces a direct surface runoff of 6.2 cm. The time distribution of the storm is given in the following table.
Time from start in hour 1 2 3 4 5 6 7 8
Incremental rainfall in each hour in cm 0.5 1.0 1.8 2.6 2.0 1.5 1.2 0.4

Compute the Φ index of the storm.
7 M

3 (a) Define runoff, sub-surface runoff and direct runoff. Explain the factors affecting runoff.
7 M
3 (b) The ordinates of flood hydrograph from a 4 hour rainfall are given below. Derive the ordinates of 4 hour unit hydrograph for a catchment area of 640 km .
Time (hours) 0 4 8 12 16 20 24 28 32 36 40
Discharge m3/s 30 68 205 410 330 254 195 133 95 58 30
7 M
Define the following in relation to aquifer
3 (c) 1 Confined aquifer
1 M
3 (c) 2 Unconfined aquifer.
1 M
3 (c) 3 Aquiclude
1 M
3 (c) 4 Aquifuge
1 M
3 (c) 5 Transmissibility
1 M
3 (c) 6 Storage coefficient
1 M
3 (c) 7 Specific yield
1 M
3 (d) A 30 cm diameter well completely penetrates a confined aquifer of permeability 45 m/day. The length of strainers is 20 m. Under steady state of pumping, the drawdown at the well was found to be 3.0 m and radius of influence was 300 m. Calculate the discharge.
7 M

Write a short note on
4 (a) 1 Rational formula for flood estimation
4 M
4 (a) 2 Flood forecasting and warning
3 M
4 (b) Explain various causes of flood and their preventive measures.
7 M
4 (c) Explain the procedure to determine the reservoir capacity using mass curve.
7 M
Describe in brief
4 (d) 1 Reservoir sedimentation
4 M
4 (d) 2 Components of power house
3 M

Write a short note on
5 (a) 1 Causes of drought
4 M
5 (a) 2 Water conservation
3 M
5 (b) Explain various methods of water harvesting.
7 M
5 (c) Explain flood frequency analysis.
7 M
5 (d) Explain functional requirements of water resources projects.
7 M