1 (a)
Discuss present energy consumption scenario of India.
7 M
1 (b)
What is energy security and what is Indian government strategy for future to
meet energy security.
7 M
2 (a)
Define the following terms: (1) Dew Point temperature (2) HCV (3) LCV (4)
Contract Demand (5) Time of Day tariff (6) Power Factor (7) Inductive load
7 M
Solve any one question from Q2(b) & Q2(c)
2 (b)
Discuss 'Post Audit' phase of Energy Audit methodology.
7 M
2 (c)
Give the format of Energy audit report.
7 M
Solve any two question from Q3(a), Q3(b) & Q3(c), Q3(d)
3 (a)
Define following financial terms: (1) Cash flow (2) time value of money (3)
capital cost (4) depreciation
7 M
3 (b)
Which tool is used to represent difference between standard consumption and
actual consumption? Explain with sample graph.
7 M
3 (c)
How to save energy by substituting existing fuel? Give some examples.
7 M
3 (d)
Explain Indirect method of Energy Efficiency calculation for Furnace.
7 M
Solve any two question from Q4(a), Q4(b) & Q4(c), Q4(d)
4 (a)
How to save energy in Refrigeration and Air Conditioning plant?
7 M
4 (b)
Discuss the effect of following parameters on the performance of Boiler
(1) Excess air
(2) Blow down
(3) Waste heat utilization
(1) Excess air
(2) Blow down
(3) Waste heat utilization
7 M
4 (c)
How to save energy in Compressed air delivery system as well as compressor?
7 M
4 (d)
How to make lighting system of your college campus more efficient?
7 M
Solve any two question from Q5(a), Q5(b) & Q5(c), Q5(d)
5 (a)
Make a list of various energy saving opportunities in Pump.
7 M
5 (b)
For an existing plant a pump replacement is planned. A pump is working for 4400 hours per year and delivers 8000 m3/hr of water at 40 m height. Two
pumps are finalized for the same. Pump A is 76% efficient and pump B is 82%
efficient with additional cost of 1lac rupees. Select the pump. Power
consumption of a pump is given by following formula. \[ \text{Power consumption }= \left ( \dfrac {p\times g \times Q \times H}{3600 \times 10^3} \right ) \]
7 M
5 (c)
Give examples of waste heat utilization where high temperature waste heat is
Available.
7 M
5 (d)
Explain topping cycle co-generation plant with sketch.
7 M
More question papers from Energy Conservation And Management