Solve any one question from Q.1 &Q.2
1
Write a note on Project monitoring & ReportingSystem.
6 M
2
Explain in detail purpose of construction sheduling.
6 M
Solve any one question from Q.3 &Q.4
3
Define. Prepare WBS for the construction of bridge across river.
8 M
4
Write short note on:
a) Application of LOB
b)Work study
a) Application of LOB
b)Work study
8 M
Solve any one question from Q.5 & Q.6
5
Explain in detail Building & other Construction Worker's act 1996.
6 M
6
Discuss the importance of child labour act in construction sector.
6 M
Solve any one question from Q.7(a,b,c) & Q.8(a,b,c)
7(a)
What are the different types of risks involved in any road project.
6 M
7(b)
Write short note on: Break Even Analysis.
6 M
7(c)
Discuss in detail the concept of risk mitigation.
6 M
8(a)
Write short note on: Risk control.
6 M
8(b)
Discuss in detail decision tree analysis
6 M
8(c)
Write short note on: Value Management.
6 M
Solve any one question from Q.9(a,b,c) & Q.10(a,b,c)
9(a)
Discuss the role of materials management.
6 M
9(b)
What are the aim & obejective of career planning.
6 M
9(c)
Discuss the importance of vendor networking in construction projects.
4 M
10(a)
A supplier has to supply 500 units of a commodity to his client every week. The cost rate is Rs. 200 per unit and ordering cost is Rs.200 per order. The carrying cost of inventory is 20% per year of the cost of inventory. Find Economical order quantity.
6 M
10(b)
Explain the improtance of buyer seller relationship in civil engineering projects.
6 M
10(c)
Write short note: Human Resource Information System.
4 M
Solve any one question from Q.11(a,b) & Q.12(a,b)
11(a)
Explain the term artifical intelligence. Discuss its benefits to construction sector.
8 M
11(b)
What do you mean by genetic algorithm? Explain with suitable example.
8 M
12(a)
Explain with example importance of ANN in construction management.
8 M
12(b)
What do you mean by fuggy loagi? State various application of fuggy logic in civil engineering.
8 M