Answer the following
1 (a)
Enlist grouting materials, grouting equipments & grouting methods used for grouting.
4 M
1 (b)
Explain the use of shaft in tunnelling.
4 M
1 (c)
What is economic life of an equipment? Explain.
4 M
1 (d)
Explain any one type of crane
4 M
1 (e)
Explain the working of power shovel
4 M
2 (a)
Explain the method of tunnelling in soft rock by 'Needle beam method' in detail.
10 M
2 (b)
Enlist all types of drilling equipments & explain any one drilling equipment in detail.
10 M
3 (a)
Determine hourly owning & operating cost of a machine from the data given below.
(a) Purchase Cost = Rs. 30 Lakhs.
(b) Useful Life = 12 years.
(c) Investment Cost = 20% of avg. Investment.
(d) Actual working = 3000 hours/ year.
(e) Salvage value. = Rs. 3 lakhs.
(f) Engine (Diesel) = 40 HP.
(g) Operating factor = 0.7
(h) Maintenance & repairs cost = Same as depreciation amount.
(i) Lubricant cost = 25% of fuel cost.
(j) Operator's Salary = Rs. 12000/- month.
(a) Purchase Cost = Rs. 30 Lakhs.
(b) Useful Life = 12 years.
(c) Investment Cost = 20% of avg. Investment.
(d) Actual working = 3000 hours/ year.
(e) Salvage value. = Rs. 3 lakhs.
(f) Engine (Diesel) = 40 HP.
(g) Operating factor = 0.7
(h) Maintenance & repairs cost = Same as depreciation amount.
(i) Lubricant cost = 25% of fuel cost.
(j) Operator's Salary = Rs. 12000/- month.
10 M
3 (b)
Explain the points to be considered while selecting a construction equipment.
10 M
4 (a)
Enlist various types of pile driving equipments. Also explain any two of them in detail.
10 M
4 (b)
What are various types of compacting equipments? Also explain all types in brief with their suitability.
10 M
Draw neat sketches for
5 (a) (i)
Stone column.
5 M
5 (a) (ii)
Grouting application.
5 M
Explain
5 (b) (i)
Pilot Tunnel
5 M
5 (b) (ii)
Lining of Tunnel.
5 M
6 (a)
A m/c is down for 4%. 6%. 8%. 10% & 12% of time respectively in first five years. Its operating cost is Rs. 1000/- hour. Machine works for 3000 hours in a year. The average productivity factor is 0.7. Workout down time cost & cumulative downtime cost.
10 M
6 (b) (i)
Explain 'Vaccum Concrete' in detail
8 M
6 (b) (ii)
Define 'Stemming'.
2 M
Write notes on following (any five)
7 (a)
Hot weather concreting
4 M
7 (b)
Concrete pump.
4 M
7 (c)
Liner plate method
4 M
7 (d)
Slip form
4 M
7 (e)
Tunnel Boring Machine.
4 M
7 (f)
Standard & special equipment.
4 M
7 (g)
Sand drain technique.
4 M