GTU Civil Engineering (Semester 4)
Concrete Technology
May 2014
Total marks: --
Total time: --
INSTRUCTIONS
(1) Assume appropriate data and state your reasons
(2) Marks are given to the right of every question
(3) Draw neat diagrams wherever necessary


1 (a) Enlist the types of cements and explain properties of PPC.
7 M
1 (b) Define standard consistency of cement and write the laboratory procedure for determining the same.
7 M

2 (a) Define initial setting time and final setting time of cement and explain the laboratory test for the same. Mention the IS limits of IST and FST of OPC.
7 M
2 (b) Give difference between Rapid hardening cement and Quick setting cement.
7 M
2 (c) Explain heat of hydration and it's importance in setting.
7 M

3 (a) Define aggregate and classify them according to (i) size (ii) Shape (iii) source of origin and (iv) Weight criteria.
7 M
3 (b) Define fineness modulus of aggregate and calculate it's value for the following test result. Explain it's utility.
IS sieve 40 20 10 4.75 2.36 1.18 0.60 0.30 0.15
% wt. Retained 5 30 50 60 80 96 99 100 100
% Passing 95 70 50 40 20 04 01 00 00
7 M
3 (c) Describe effect of impurities in water on properties of concrete.
7 M
3 (d) Enlist the purposes of using admixture in concrete.
7 M

4 (a) Define workability of concrete and explain any one test to measure the workability of concrete.
7 M
4 (b) Explain segregation and bleeding phenomenon. Also write the causes of Segregation.
7 M
4 (c) Define the "Mix design" and design concrete mix M20 using following data and IS : 10262 procedure.
1. Max. size of aggregate = 20 mm
2. Degree of workability = 0.80 CF
3. Degree of quality control = good
4. Type of exposure = mild
5. w/c/ = 0.47
6. Cement used = OPC 53 grade
7. Sp. Gravity of cement =3.15, Coarse aggregate = 2.70, Fine aggregate =2.65
8. Water absorption of Coarse aggregate = 0.5 %, Fine aggregate = 1.0 %
9. Free moisture in C. A. = 0.0 % , F. A. = 0.0 %
10. Bulk density of Cement = 1440, C. A. = 1650, F.A. = 1800 kg/m3
7 M

5 (a) Write note on NDT and it's utility
7 M
5 (b) Write note on (i) Hot weather concreting (ii) Recycled aggregate concrete.
7 M
5 (c) State causes and precautions for distress in structures.
7 M
5 (d) Explain with sketch crack repair by injection grouting.
7 M