Solve any four:
1 (a)
What are PMBOK knowledge areas?
5 M
1 (b)
Compare various project implementation approaches
5 M
1 (c)
What is the need of IT project management ?
5 M
1 (d)
Compare various formula organizational structures
5 M
1 (e)
Define 1) Scope grope 2) Scope creep 3) Scope leap 4) Projectitis 5) Earned value
5 M
2 (a)
Define project. Explain the attributes of project
10 M
2 (b)
Explain project estimation technique
10 M
3 (a)
Explain the phase of project life cycle. Compare it with SDLC
10 M
3 (b)
What is outsourcing? Explain project procurement management
10 M
4 (a)
Explain IT project risk identification framework
10 M
4 (b)
Explain the change management plan
10 M
5 (a)
Explain the practices of exemplary leadership. What are the leadership style?
10 M
5 (b)
Explain scope management process
10 M
6 (a)
Explain project planning framework
10 M
6 (b)
Define critical path. Draw AON diagram, find critical path and float for non critical path the following.
Activity | Predecessor | Duration in days |
A | - | 6 |
B | A | 5 |
C | A | 8 |
D | B,C | 4 |
E | C | 3 |
F | D | 2 |
G | D | 4 |
H | E,F,G | 7 |
10 M
Write short note on (any two)
7 (a)
Ethical leadership and ethical dilemmas
10 M
7 (b)
Resource loading
10 M
7 (c)
Project communication management
10 M
7 (d)
Work break down structure
10 M