1 (a)
Explain under which conditions pile foundation is preferable?
7 M
1 (b)
Which points can be considered while selecting the type of pile?
7 M
2 (a)
Differentiate between End bearing pile and Friction pile.
7 M
2 (b)
Write short note on sand piles with its advantages and disadvantages.
7 M
2 (c)
Discuss various causes of failure of piles.
7 M
3 (a)
What is Coffer Dam? State requirements of a coffer dam.
7 M
3 (b)
Describe with sketch single walled cofferdam.
7 M
3 (c)
Write short note on cellular cofferdam.
7 M
3 (d)
Explain the ways by which the leakage can be prevented in coffer dams.
7 M
4 (a)
Write short note on box caisson with sketch.
7 M
4 (b)
What do you mean by pneumatic caisson? Discuss its construction procedure
with sketch.
7 M
4 (c)
Write short note on tilting of caissons.
7 M
4 (d)
What is caisson sickness or diseases? What are the precautions to be taken to
avoid caisson sickness?
7 M
5 (a)
Explain cement grouting to control ground water in excavations.
7 M
5 (b)
Write short note on slip formwork.
7 M
5 (c)
Discuss planning of earthquake resistant building.
7 M
5 (d)
Write short note on demolition plan.
7 M